Plan-Set Controls
Client
Anonymized: 9–15 homes/year, mountain modern
Industry
Custom Builder
Year
2025
Duration
3 weeks
(01)
Project overview.
An agent that watches plan folders for new PDFs, runs vector diffs, maps each change to cost codes/tasks/inspections/open RFIs, and drafts one-page “Change Briefs” per trade (before/after snippet, what changed, action, due date). It pings only the affected stakeholders via text/email, requires one-tap “Got it,” rebuilds the two-week look-ahead, and updates allowances/PO drafts and cash forecasts when pricing is impacted.
(02)
Challenge.
Crews were building from outdated sheets, plan changes weren’t priced into allowances promptly, and subs learned about revisions days late—causing out-of-sequence work and margin leakage.
Results
(03)
Result.
Impact in 30–60 days:
• “Built from the wrong set” incidents: 0 (was 2–3/quarter)
• Days saved per home: 3–7 (prevented out-of-sequence work)
• Margin leakage from unpriced plan changes recovered: +$8k–$20k/home
• Median acknowledgment time on changes: ~1.1 hours (was 24–48 hours)